Network News

Turk Heavy Transport Performs Multimodal Transportation of 14 Units Steam Turbine Generator & Generator Step-up Transformer for Water & Power Plant in Bahrain

12:00am 18th March 2022

https://doc.x2logisticsnetworks.com/news/news__18032022_E_NEWS_TURK.jpg

SHARE THIS ARTICLE

Facebook

Twitter

LinkedIn

https://doc.x2logisticsnetworks.com/news/news__18032022_E_NEWS_TURK.jpg

As part of this project, Turk Heavy Transport successfully delivered several Steam Turbine Generator& Generator Step-up Transformers, weight ranging from 207 MT to 343 MT per piece. During the arrival of the shipment in Bahrain, the Turk team received the shipment from the ship hook and placed them on the stools support to complete the customs formalities, on a later date it was rolled directly from the port to the barge and the same method was performed during discharge at the private jetty. From the Private Jetty to the project site cargo was transported by road. A Self-Propelled Modular Transporter was used.

With the critical overweight in mind, this movement was meticulously planned. Their technical & project operations team communicated with the client in advance about the civil works required at their premises to ensure a smooth operation.

A detailed route survey was conducted, during which the technical team considered various metrics, including turning radius, several calculations to ensure safe transportation, and local permits were also obtained in advance to ensure timely delivery of the cargo.

Civil works were also carried out en route from the Private Jetty to the project site. There were two barging operations to complete the deliveries. Well done on your execution! Congratulations!